OEE is a measurement used in Total Productive Maintenance programs. The measure includes machine effectiveness and efficiency and is a metric commonly found in Lean Manufacturing. It helps answer three questions:
The formula for calculating OEE is shown below:
The following defines the three components along with an example later on this page.
AVAILABILITY (A):
Availability is the unit of time the machine is available to run divided by the total possible available time. This metric does not include any performance numbers relative to how the machine runs while it is running.
AVAILABILITY = Operating Time / Planned Production Time
This is different than another common metric called Utilization. Availability only includes the time the machine was scheduled, planned, or assigned to run.
Utilization can include all hours of the day regardless of schedule. Utilization is more effective in capacity planning and analyzing the absorption of fixed costs. Availability looks at the machine itself and focuses more on variable cost absorption.
Operating time = Planned Production Time - Planned Downtime
Planned downtime includes lunch breaks, meetings, and any other regularly scheduled breaks that are independent of the machine.
PERFORMANCE (P):
Sometimes referred to as Efficiency, is a measure of how good the machine runs while it is running (within the operating time).
PERFORMANCE = Pieces Produced / (Ideal Speed * Operating Time) * 100%
QUALITY (Q):
Quality is a measure of the number of parts that are within specification compared to how many were produced.
In some cases, there is "PLANNED" scrap production or "PROJECTED" scrap.
"PLANNED" scrap is a troublesome term to use because all scrap is lost profit even if it is built into the quote and cost. If a competitor figures out how to eliminate it then you create a disadvantaged cost structure and winning new business becomes more unlikely.
For example, if the machine must warm-up for a few pieces or learn a process than these pieces should not be included in the calculation. HOWEVER, this does represent opportunity. Finding a way to permanently avoid these warm-up pieces or initial scrap pieces is a credible improvement.
QUALITY = Acceptable Pieces / Total Pieces * 100%
Total Pieces = Acceptable Pieces + Unplanned Scrap Pieces
A challenge within bulk production processes is that pieces from one operation may not be recognized as defective until later downstream. In not all cases, 100% inspection of 100% of the criteria is practical, so defects may be found downstream of the machine that actually created them.
This means that actually the Quality portion of OEE for that machine would need to be recalculated with the lower value of Acceptable Pieces.
Let's assume the following information has been compiled by a Six Sigma team:
Calculate the OEE over an 8 hour shift that had:
Let's calculate each element of OEE:
AVAILABILITY (A):
There are a total of 480 minutes in one shift. 50 more minutes were planned so those minutes will be removed from the denominator.
So the denominator in Availability becomes (480-50) / 480 = 430 minutes (this is the Planned Production Time)
The numerator is the Operating Time which removes the total Unplanned Downtime which was only 10 minutes related to a tooling failure. So the Operating Time was 420 minutes
Thus A = 420 minutes / 430 minutes = 97.67%
NOTE: Keep in mind, another common metric measured by companies is UTILIZATION. In this case, Utilization would be 420 / 480 = 87.5%. In other words, regardless of the reason for lost downtime, the equipment was utilized on 87.5% of the potential time during the shift.
PERFORMANCE (P):
This answers the question, how well did the machine run when it was running? The key words are "when it was running" Therefore, the denominator is looking at the 420 minutes of run time.
If the machine was supposed to run 400 pieces per minute, multiply that by 420 minutes to get the amount of pieces that should have been made, which is 168,000 pieces.
The machine actually made 150,000 pieces. Therefore there must have been some losses (see the "losses" explained below).
Thus P = 150,000 pieces / 168,000 pieces = 89.29%
QUALITY (Q):
Since there were 25,000 pieces scrapped that means 125,000 out of the 150,000 were acceptable.
Thus Q = 125,000 / 150,000 = 83.33%
To get the OEE, multiply A * P * Q:
OEE = 97.67% * 89.29% * 83.33% = 72.7%
These six areas of losses impact OEE and its three components. Breaking down the losses to these categories helps the Six Sigma team prioritize improvements. The losses affect one of the three products (A, P, or Q) and the area with the lowest percentage is likely a good place for the team to focus its improvements.
Breakdown Losses
Sudden or unexpected equipment failures that make the machine less available. Contributing factors include:
Set-up & Adjustment Losses
Downtime and defective product that occurs when production of one part stops and the equipment is set-up/adjusted to meet the requirements of another part. The degree of loss depends on factors such as:
Idling & Minor Stoppages
Production is interrupted by a temporary malfunction or when the machine is idling. Contributing factors include:
Start Up Losses
This type of loss is a yield loss that occurs during the early stages of production - from machine start-up, warm-up, "learning phase" to the point where the machine is producing regular, quality production. The degree of loss depends on factors such as:
Reduced Speed Losses
Refers to the difference between equipment design speed and the actual operating speed. Some parts may not be able to run at a machines maximum rate (for example, machine can run large ranges of parts and larger parts may have to run slower per the OEM manual - so an ideal rate for each part should be established). Factors include:
Quality Defects (Scrap & Rework)
Losses in quality caused by malfunctioning equipment or tooling. The degree of loss depends on factors such as:
The definition of "World Class" depends on several factors and the exact inputs to the calculation. World Class OEE is shown differently by many authors and companies. It is a relative value, as competition increases and expectations increase the acceptable value for "World Class" OEE is driven higher.
Most importantly when improving OEE is to use a consistent and standard definition. Include your team's definition on the Data Collection Plan and the Control Plan. This applies for any metric definition for which there is varying industry accepted formulas.
A company producing pencils may have an acceptable quality level of 95.00%. If your company is producing aircraft tires then 99.9999% may be a minimum world class level.
Some general guidelines are shown below. What matters most is "Is OEE improving"?
But like any metric it should be defined with a clear understanding of the inputs, its meaning, and the types of decisions that could result. As a Six Sigma Project Manager, you need to ensure the metric will drive the best overall decisions.
There isn't a single metric that explains productivity, efficiency, and scrap but this is one clever attempt. Those three buckets are large in scope and require clarity to allow an OEE value to provide fair and meaningful information.
Many factors create complexity from variable speed machines, parts that can run at different rates on different machines, and "planned" scrap such as done while a machine is tuned in, warming up, or learning tolerances.
With all of these factors influencing OEE in most cases (including people and parts themselves) it may be more appropriately coined as Overall Production Effectiveness.
|
|
It's most important that everyone (stakeholders) using your OEE metric is educated on how it is calculated and what is included and excluded. This prevents unnecessary questions allowing everyone to concentrate efforts on improvements.
And there will always be gray areas where it makes sense to have this-or-that in the formula but at some point your company or team has to define the metric and stay consistent.
Once it is defined, spend time to educate the stakeholders and have them do a couple sample calculations to solidify its understanding.
When there is disagreement on OEE as it is defined, it's at least good enough to provide a directional metric. This mean that by measuring OEE consistently over time and across all machines can tell you if the machine OEE is getting better or worse even if the number is extremely high or low relative to "world class".
That is more important than trying to determine if a % if good, bad, world class, etc. The question is are you getting better or worse?
It can also be used to compare among similar types of machines and among all machines. An ANOVA study can be used to see if the variation is coming from within a group of machines or among them all.
In summary, measure OEE consistently across the company and use it for directional purposes (rather than comparing company to company unless one is sure the measurement and calculations are exactly the same).
An OEE calculator with an example and explanations is available by clicking here.
OEE and its straight percentages can be misleading. It is very rare that one metric can tell the entire story regardless of how encompassing its formula may seem. There is always a human element needed to check and balance the numbers.
Also, be aware that you can add a lot of labor and manpower (costs!) and this will likely improve OEE. It is important to improve a metric without sub-optimizing others.
For example:
Lets say there are two machines that can run a particular part and assume Availability and Quality are equal for each machine.
MACHINE 1 and MACHINE 2 given info:
Availability: 93.75% (both operate 7.5 hours out of 8 hours planned)
Quality: 90.00% (both make 10,000 unplanned scrap pieces + 90,000 acceptable pieces when making a total of 100,000 pieces)
Let's say:
MACHINE 2 is newer and equipped with better technology thus can run the same parts faster without sacrificing quality levels.
Normally the part is always scheduled in MACHINE 2 because it gets the same Quality level and Availability AND it runs much faster than MACHINE 1.
The typical Performance is MACHINE 2 is 225 pieces/minute when over operating time of 450 minutes (7.5 hours) thus produces 101,250 pieces.
However, if MACHINE 2 is full or down for repair on that day, it is sent to MACHINE 1 to run.
Through the same 450 minutes, MACHINE 1 makes a total of 87,750 pieces and this is an average of 195 pieces/minute.
Looking at straight percentages of Performance:
NOW, calculating each OEE:
Sounds great....right?
MACHINE 1 has better OEE and the part should be produced there? NO
195 pieces/minute is not acceptable when it normally runs at 225 pieces/minute in MACHINE 2 at the same Quality and Availability levels.
This is even more important when the part is quoted at the rate of 225 pieces minute to give the company the best chance to win the job. The company knows upon quoting that this type of part should run at 225 so anything less is going to reduce the margin - assuming everything else is constant.
Someone may suggest, "use 250 pieces/minute as the ideal rate in the denominator when calculating the performance for MACHINE 1", but then this is not truly the MACHINE 1 overall equipment effectiveness. MACHINE 1 did what it was supposed to do, after all 97.5% is very good.
The company should keep this part in MACHINE 2 and work to reduce the speed losses to increase the Performance level to that of MACHINE 1.
In other words, if the measurement of OEE is pushed too hard, that may incline operators and supervisors to simply run the parts on a machine with a slower maximum or ideal speed just to show a higher OEE.
Use TPM or better capacity planning to get closer to the root cause as to why the part couldn't be produced in MACHINE 2. Those KPIV's are the inputs a team should correct, prevent, and control.
Click here for more insight on OEE as is pertains to this international automotive standard as component of Section 8.5.1.5 of TPM.
Metrics such as OEE, MTTR, and MTBF are increasing their presence in the manufacturing throughout the world.
Subscribe to get access to all modules this site
Six Sigma
Templates, Tables & Calculators
Six Sigma Slides
Green Belt Program (1,000+ Slides)
Basic Statistics
Cost of Quality
SPC
Process Mapping
Capability Studies
MSA
SIPOC
Cause & Effect Matrix
FMEA
Multivariate Analysis
Central Limit Theorem
Confidence Intervals
Hypothesis Testing
T Tests
1-Way ANOVA
Chi-Square
Correlation
Regression
Control Plan
Kaizen
MTBF and MTTR
Project Pitfalls
Error Proofing
Z Scores
OEE
Takt Time
Line Balancing
Yield Metrics
Sampling Methods
Data Classification
Practice Exam
... and more