Line Balancing

Description

Line Balancing is leveling the workload across all processes in a cell or value stream to remove bottlenecks and excess capacity. A constraint slows the process down and results if waiting for downstream operations and excess capacity results in waiting and no absorption of fixed costs.

Objective

Match the production rate after all wastes have been removed to the Takt time at each process of the value stream.

EXAMPLE:

Taking the example from the Takt time page as the starting point, there were additional studies conducted each the remaining processes that it takes to make UNIT ABC.

  • There are five processes in the workcell dedicated to only UNIT ABC.
  • Each process has same demand and available work time = same Takt time. The LOADING data was found using historical production data of ACCEPTABLE parts only including downtime but only when the processes were scheduled with operator(s). 
  •  The customer only wants acceptable parts and that is what the customer demand is based on within the Takt time formula. When figuring the production rates (loading) the scrap or non-conforming pieces must be netted out.

  • Line Balancing


    Often the bottlenecks or areas of excess capacity are known by the team members but this analysis provides the quantitative data to prioritize activities to improve.

    Line BalancingSix-Sigma-Material.com


    Process 1: Taking much longer than Takt time. Overtime is probably used to make up production and is the #1 constraint.

    Process 2: Exceeding the Takt time, probably a lot of waiting and the excess capacity can be filled by absorbing some of the work from Process 1 and/or Process 4.

    Process 3 & 5: Very close to meeting Takt time, not a focus area but possibly some best practices and application of LEAN tools can improve these loading rates. Improvement in these areas could be used to share workload from constraint processes.

    Process 4: Taking longer than Takt time. Again, overtime is probably used or there are late deliveries, high expediting costs or unhappy customers. Apply Lean Manufacturing principles and try to alleviate workload to Process 2 or others that may be able be improved to absorb some of the workload.

    Examine all the specific activities occurring in each process. Time studies, motion studies, and other Lean tools often provide most the ideas for improvement.

    Develop a plan for immediate, low-cost improvements. Professional signage, advanced comprehensive training and capital investments are not needed or justified yet.

    Run studies to determine the potential LOADING improvements. There is most likely not much that can be done to change the Takt time; focus on improving the LOADING (production rate).

    Improving the LOADING, even in non-constraint operations is desirable, but the top priority is relieving constraint operations.


    AFTER

    The table and chart below shows the results of the Line Balancing improvements.

  • Visual Management tools added to improve consistency of units produced.
  • Standard Operating Procedures (SOP) and training were done for all operators.
  • SMED activity was done on all operations with focus on Process 1.
  • Point-of-use tooling and shadow boards were implemented.
  • Kanbans were established for materials.
  • Some steps in each process were found no longer necessary.
  • The machines in a couple operations received upgrades and overdue minor rebuild and were added to a TPM program. There speeds were dramatically improved (the "performance" component of OEE).
  • Error-proof jig to prevent defects and rework was implemented.
  • And/on lights were added as communication signals.
  • 5S event held with key stakeholders. 
  • There were gains...and the success was to the point where there was excess capacity. All the activities could now be completed in four processes. Floor space was gained and excess older and fully depreciated equipment were sold for cash.

    A new loading study was done and the results are shown.

    Recall, the goal of Line Balancing is to have the loading rates meet the Takt time and this is accomplished as the chart indicates.

    Final Result of Workcell Line BalancingSix-Sigma-Material.com

    Takt Time and Line Balancing Calculator

    A Takt Time and Loading calculator with an example is available here. Within the file are explanations to assist with completing the template. 



    Return to Takt Time

    Return to LEAN MANUFACTURING

    Templates, Tables, and Calculators

    Subscribe for access to entire site

    Return to Six-Sigma-Material Home Page 



    Site Membership
    Click for a Password
    to access entire site
    


    Six Sigma
    Templates & Calculators


    Six Sigma Modules

    The following are available 

    Click Here

    Green Belt Program (1,000+ Slides)

    Basic Statistics

    Cost of Quality

    SPC

    Process Mapping

    Capability Studies

    MSA

    Cause & Effect Matrix

    FMEA

    Multivariate Analysis

    Central Limit Theorem

    Confidence Intervals

    Hypothesis Testing

    T Tests

    1-Way ANOVA

    Chi-Square

    Correlation and Regression

    Control Plan

    Kaizen

    MTBF and MTTR

    Project Pitfalls

    Error Proofing

    Effective Meetings

    OEE

    Takt Time

    Line Balancing

    Practice Exam

    ... and more